Pouring concrete in a North Texas winter: freeze-season rules
By Wade Sutton, North Texas construction specialist: the Blackland Prairie clays and Cross Timbers sands that decide how concrete and site work perform here, the TxDOT and city permitting rules on both sides of the Red River, and what belongs in a written project scope. Published November 13, 2026.
Winter pours in Gainesville, Sherman, and Denison go fine when the cold is planned for. The 40 degree line, the 500 psi rule, and lessons from 2021.
Questions about general construction? Call or text us.
Call (903) 308-5497Your slab or driveway is scheduled for December, and the ten-day forecast shows a blue norther. Winter pours are routine in North Texas, and they go well when the plan treats cold as a certainty rather than a surprise. Here is what the concrete industry's own guidance says, and what February 2021 taught everyone who builds here.
When "cold weather" starts
The National Weather Service puts the average first freeze at DFW Airport on November 22 and the average last freeze on March 12, and the Red River counties sit north of that station. So a pour between Thanksgiving and mid-March should be planned as a cold-weather pour, even if the day itself turns out mild.
The American Concrete Institute's cold weather guide, ACI 306R-16, defines cold weather as any time the air temperature has fallen to, or is expected to fall below, 40 degrees during the protection period, the days after placement when fresh concrete is still vulnerable. The forecast for the next several nights matters as much as the temperature at the truck.
The 500 psi rule
Fresh concrete is saturated with water. If that water freezes before the concrete gains enough strength, the ice expands inside the paste and damages it permanently. The National Ready Mixed Concrete Association notes that fresh concrete freezes at about 25 degrees and that frozen concrete can lose more than half its potential strength.
ACI's guidance draws the line at a compressive strength of 500 psi. Concrete protected from freezing until it reaches that strength will not be damaged by a single freeze, and at 50 degrees most well-proportioned mixes get there within 48 hours. The practical rule: keep a new slab above freezing for at least the first two days, longer if the weather is colder than that.
A winter pour, done right
Before the truck arrives
- Remove any frost, snow, or ice, and never place concrete on frozen ground; NRMCA's cracking guidance says so plainly, and a frozen subgrade settles as it thaws.
- Have insulated blankets on site before the pour, not ordered after it. Edges and corners lose heat first.
- Order the mix for the weather. For thin sections like slabs and driveways, NRMCA recommends concrete placed at 55 degrees or warmer.
During placement
- Place at the lowest practical slump, and do not add water at the truck to make it flow. Extra water delays setting and prolongs bleeding, which holds up finishing.
- Expect slower setting. As a rule of thumb, a 20 degree drop in concrete temperature roughly doubles setting time, so finishing runs later into the day.
- Accelerators help, within limits. Calcium chloride should stay at or below 2 percent by weight of cement, and non-chloride accelerators are the safer choice around reinforcing steel. No accelerator prevents freezing.
After finishing
- Cover with blankets once the surface can take them, and use a curing compound or plastic rather than water curing when a freeze is coming.
- Remove protection gradually. ACI recommends letting the surface cool over about 24 hours rather than pulling blankets on a cold morning.
- Keep deicing salts off new concrete through its first winter. NRMCA lists heavy deicer use on new, saturated concrete among the main causes of surface scaling.
Our FAQs on foundation cure time and driving on new concrete cover the weeks after the pour, and the driveway thickness guide covers the spec underneath it.
What February 2021 taught builders
The Weather Service's summary of the February 2021 storm is a planning document in disguise. DFW Airport stayed at or below freezing for 93 hours from February 9 to 13, then for another 139 consecutive hours from February 13 to noon on February 19. It hit minus 2 degrees on February 16 and recorded 5 inches of snow.
Nobody pours concrete in a week like that. The lessons show up in the design of what gets built the rest of the year:
- Plumbing belongs inside the insulated envelope. Supply lines in exterior walls, unheated attics, and uninsulated garage ceilings are the most exposed to a long freeze. New work and remodels can route them inside.
- Hose bibbs and exposed lines need freeze protection. Frost-free sillcocks and insulated risers are cheap during construction.
- Backup power is now a real line item. The 2025 Cost vs. Value report puts a backup generator in the Dallas market at about $12,818, and Sherman requires a permit for permanent generator installations.
- Shops and barns need a heat plan. An exposed water line in an unheated metal building is usually the first thing to freeze.
Scheduling around the holidays
The weeks between Thanksgiving and New Year's compress everything. City permit offices close for holidays, inspections book up ahead of them, and ready-mix suppliers may run holiday hours. If a pour depends on a pre-pour inspection, schedule that inspection first and build the pour date around it, with a backup date the following week for weather. It is better to hold a formed slab through a cold front under blankets than to rush a pour ahead of one.
For slabs, shop floors, and foundations in Gainesville and across Cooke and Grayson counties, the concrete foundations and slabs service in Gainesville writes the cold-weather plan into the scope: blankets, mix, cure method, and the hold points. Call or text with your target pour date and we will talk through what the weather means for it.
Sources cited
- ACI 306R-16 Guide to Cold Weather Concreting (excerpt)
- American Concrete Institute: cold weather concrete resources
- NRMCA Concrete in Practice 27: Cold Weather Concreting
- NRMCA Concrete in Practice 2: Scaling Concrete Surfaces
- National Weather Service Fort Worth: February 2021 winter storm
- National Weather Service Fort Worth: DFW freeze summary
- Journal of Light Construction 2025 Cost vs. Value: Dallas
- City of Sherman: Permits Required