case study · 4 min read
Site preparation in McKinney and Collin County, step by step
By Wade Sutton, North Texas construction specialist: the Blackland Prairie clays and Cross Timbers sands that decide how concrete and site work perform here, the TxDOT and city permitting rules on both sides of the Red River, and what belongs in a written project scope. Published October 23, 2026.
A scenario walk-through of taking a Collin County lot from pasture to pad: permits, stormwater rules, tree permits, clay pads, and the drainage survey.
Questions about general construction? Call or text us.
Call (903) 308-5497Picture a 2.5-acre tract of old pasture east of McKinney, just outside the city limits, with a new house planned near the road and a 30 by 40 shop behind it. The owner's first question is usually when the dozer can start. The better first question is which office governs the dirt, because in Collin County that answer changes what happens before, during, and after the machines arrive. This scenario walks the sequence from paperwork to a finished pad.
Step 1. Find out which rulebook applies
Inside McKinney, site work rides along with city permits filed through the Citizen Self-Service portal. Outside the city in unincorporated Collin County, the county's Development Services office requires a development permit for any project that disturbs ground or adds footprint, whether that is a house, a barn, an addition, or a pool. The county does not assign addresses to raw land; the address comes through that permit.
For our scenario tract, three county rules shape the plan before any design work:
- Septic comes with the development permit. For a new home, the septic permit attaches to the development permit, and lots divided in 2008 or later need at least 1 usable acre for an on-site system.
- Third-party inspections are required. The county requires an independent inspector on new homes and substantial additions.
- Floodplain is a hard line. Under the county's 2024 floodplain order, new homes may not be built in the mapped special flood hazard area, and homes next to it must sit at least 2 feet above base flood elevation.
If the tract were inside McKinney, the list would change: a tree permit from the Planning Department where protected trees are affected under Section 404A of the city's development code, an engineered foundation plan with a structural engineer's letter, a form board survey before plumbing rough-in, and a final drainage survey no more than 30 days old at the end of the job.
Step 2. Stormwater rules start before the first tree falls
Clearing, pad building, and a long driveway on 2.5 acres can easily disturb more than an acre of soil. Under the Texas Commission on Environmental Quality's construction general permit, TXR150000, sites that disturb at least 1 but less than 5 acres must post a site notice and put a stormwater pollution prevention plan in place before construction begins. At 5 acres or more, or as part of a larger development plan that size, the operator files a notice of intent. The current permit runs from March 5, 2023, to March 5, 2028.
In practice that means silt fence or other controls go in on the downhill side before the clearing crew starts, and a stabilized construction entrance keeps mud off the county road. It is cheaper to plan than to explain.
Step 3. Clear, grub, and strip
Old Collin County pasture often carries cedar, hackberry, and fence-row brush. Everything organic comes out of the building footprints by the roots, and topsoil is stripped and stockpiled for final grading. Buried roots and topsoil left under a pad decompose and settle, usually after the slab is on them. Our site preparation FAQ lists what a complete clearing and earthwork scope should include.
Step 4. Build the pads on clay
Much of eastern Collin County sits on Blackland clay that swells when wet and shrinks when dry. The pads for the house and shop are built up in lifts, each one moisture-conditioned into the range the geotechnical report calls for and compacted before the next goes down. Where the foundation design calls for it, imported select fill caps the native clay. A proof roll with a loaded truck finds soft spots while they are still cheap to fix. The shop pad follows the same discipline as the house pad; our post on building a pad for a shop covers that sequence in more detail.
Timing matters on this ground. Clay can only be compacted properly inside a narrow moisture window, so a week of fall rain can pause pad work. A schedule that expects it is more honest than one that pretends otherwise.
Step 5. Utilities and drainage, before the slab
Water, power, and septic lines are trenched and bedded while the ground is open, and conduit sleeves go under future driveways. The grading plan routes water around both pads, with finished grade falling away from each building and a swale carrying the pasture's runoff past the shop rather than into it. Where the driveway crosses the bar ditch at the county road, the culvert is sized for the water that actually crosses. The drainage planning FAQ covers how that plan gets drawn.
Step 6. Hand off and document
The pads hand off to the foundation work at the elevation and compaction the plans call for, and the third-party inspections the county requires pick up at the foundation. If the tract were in McKinney, the final drainage survey would confirm the finished grades before the city signs off. In either case, the owner ends up with a record of what was built under the slab, which is the part no one can inspect later.
What changes the price
Tree density, how much cut and fill the site needs, whether select fill is imported, the length of the driveway, the culvert, and stormwater controls all move a site preparation budget. A written scope lists each as its own line.
For a real lot, the site preparation service in McKinney starts with a walk of the property and a read of which office governs it. Our permit breakdown for Grayson County and its neighbors covers the county line to the north. Call or text us with the parcel and what you plan to build, and we will lay out the sequence for your ground.